1#及地下车库测量方案 联系客服

发布时间 : 星期五 文章1#及地下车库测量方案更新完毕开始阅读ebe5615c854769eae009581b6bd97f192279bfd6

目 录

1、编制依据 ················································································ 2 2、工程概况 ················································································ 2 3、施工安排 ················································································ 2

3.1建立健全测量管理制度 ········································································· 3 3.2人员配备 ··························································································· 3 3.3人员分工 ··························································································· 4

4、施工准备 ················································································ 4

4.1技术准备 ··························································································· 4 4.2仪器配备 ··························································································· 4 4.3现场准备 ··························································································· 4

5、主要测量方法 ·········································································· 4

5.1测量放线原则 ····················································································· 4 5.2.测量控制桩点的设置、保护及复测 ························································· 5 5.3.施工中的测量控制 ·············································································· 5

6施工过程中的质量保证措施 ·························································· 8 7.施工测量管理 ··········································································· 8

7.1.测量管理制度 ···················································································· 9 7.2.复核验线制度 ···················································································· 9

8、沉降观测 ·············································································· 10

第 1 页共 11 页 - -

1、编制依据

序号 1 名 称 惠友·万悦城商住小区1#楼及地下车库施工 图纸 2 3 4 《惠友·万悦城商住小区施工组织设计》 《工程测量规范》 《建筑工程资料管理规程》 GB50026-2007 DB13(J)/T145-2012 5 《经纬仪检定规程》 JJG949-2011 编 号 2、工程概况 序号 项目 l 2 3 4 5 6 7 8 本工程位于保定市涿州市,建设用地位于涿州亨通街以东,诚信路以南,相对标高±0.000相当于绝对标高32.950米。1#建筑高度50.45m,地上十七层,地下一层。1#楼建筑总面积11445.76㎡,其中地下室建筑面积749.56㎡,地上建筑面积10696.2㎡。1#地下一层层高3.40m 平时为戊类储藏间;地上一层层高3.50m为商业网点;2-17为住宅,其中2-16层层高2.90m,17 第 2 页共 11 页 - -

内 容 惠友·万悦城商住小区1#楼住宅楼 涿州市亨通街以东诚信路以南 涿州市惠友房地产开发有限公司 保定广成建筑设计有限公司 涿州市工程建设监理有限公司 涿州市建设工程质量监督站 天保建设集团有限公司 工程名称 工程地址 建设单位 设计单位 监理公司 质量监督 质量目标 施工单位 层层高2.80m;住宅室内外高差0.45m。建筑规模:中型,建筑设计使用年限50年,建筑耐火等级地下为一级,地上为二级。结构类型钢筋混凝土剪力墙结构,基础为:筏板基础。抗震设防烈度7度。建筑物安全等级为二级。

车库为地下一层,建筑总面积13716.31㎡,其中地下车库建筑面积13614.03㎡,出地面楼梯102.28㎡。地下一层层高3.40米,为一类汽车库,停车数量374辆;人防电站层高4.4米,出地面楼梯间2.7米。结构类型为板柱---剪力墙结构;建筑设计使用年限为3类(50年);基础设计等级为乙级;建筑抗震设计类别为标准设防类<丙类>,结构抗震等级:板柱结构为三级,并按二级采取抗震构造措施,抗震设防烈度7度;建筑耐火等级:地下为一级,地上为二级;地下车库防水等级为一级,地上为二级;建筑物安全等级为二级。

3、施工安排

3.1建立健全测量管理制度

甲方提供的红线桩和坐标、水准点核验,现场测量控制网(含平面主轴线和水准点),地面标高方格网,测量放线均由项目部测量负责人负责组织和主持,放线工负责实施,项目质量部负责验线,项目部验线合格后,报监理公司,未经监理公司签认不得进行下道工序。

在整个工程测量过程中,项目部测量负责人向放线工提供平面控制网和高程控制网的点位,放线员负责具体施工测量放线,测量负责人对放线工的工作实施监控和管理。技术负责人和测量负责人必须监控测量工作的原始记录,施测人员必须签字,且不得随意涂改和损坏。对原始资料和测量成果资料由资料员妥善归档保管。 3.2人员配备

考虑该工程的楼层高,对人员的选用严格把关,本工程项目部设测量负责人一名,放线工两名。所有参加施测的人员必须持有相应的上岗证。

第 3 页共 11 页 - -

3.3人员分工

测量负责人负责轴线控制线和高程控制线的检查验收。抽查细部放线的正确性。放线工负责具体测量工作。

4、施工准备

4.1技术准备

协助规划进行建筑物进行定位,并办理接桩手续,同时进行建筑物定位桩的校核。 4.2仪器配备

要作好施工控制测量工作,仪器是保证。为满足测量精度的要求,测量器具必须经过专业检测部门检测,保证其在检定期内。测量器具配备表如下

序号 1 2 3 4 5 6 7 名称 经纬仪 自动安平水准仪 激光铅垂仪 大钢尺 塔尺 线坠 靠尺 规格 J2 S3 50m 1kg 数量 1台 1台 1台 2把 1根 2只 3根 精度要求 2″ 2″ 1/40000 Ⅰ级 4.3现场准备 4.3.1配合放线人员进行钉桩工作,并及时对钉好的桩位及桩点进行保护。 4.3.2清理妨碍测量仪器通视的障碍物。 5、主要测量方法 5.1测量放线原则 第 4 页共 11 页 - -