砂石骨料供应系统施工组织方案 联系客服

发布时间 : 星期一 文章砂石骨料供应系统施工组织方案更新完毕开始阅读f05a4955a48da0116c175f0e7cd184254a351b54

目 录

卷 首 语 ................................................................................................................................ 1 文件七 概况(工程概况、编制依据、施工总体目标) .......................................................5

7.1工程概况 ...................................................................................................................5 7.2. 编制依据 ................................................................................................................ 7 7.3 施工总体目标 ......................................................................................................... 8 文件八 施工方案 ................................................................................................................ 10

8.1施工总平面布置 ...................................................................................................... 10 8.2 施工总进度及主要节点工期 ................................................................................ 15 8.3砂石料生产系统的设计 .......................................................................................... 17 8.4砂石料系统土建及金属结构安装 ............................................................................25 8.5系统生产运行管理 .................................................................................................. 34 文件九 生产进度计划 ........................................................................................................ 53

9.1生产计划编制依据 .................................................................................................. 53 9.2生产总进度 ............................................................................................................ 53 9.3生产进度计划典型强度曲线图 ............................................................................... 53 9.4生产关键线路 ......................................................................................................... 54 9.5生产进度保证措施 .................................................................................................. 54 文件十 质量保证措施 ........................................................................................................ 56

10.1质量方针 ................................................................................................................ 56 10.2质量目标 ............................................................................................................... 56 10.3质量保证体系及组织机构 ..................................................................................... 56 10.4质量保证措施 ........................................................................................................ 61 10.5质量检测 ............................................................................................................... 64 10.6试验设施 ............................................................................................................... 66 文件十一 安全文明施工 ...................................................................................................... 68

11.1安全文明施工管理目标 .......................................................................................... 68 11.2安全文明管理制度建设.......................................................................................... 69

11.3安全施工保证体系 ................................................................................................. 71 11.4文明施工保证体系 ................................................................................................. 72 11.5安全管理机构 ........................................................................................................ 74 11.6主要配置人员及素质 ............................................................................................. 75 11.7安全防洪、各类防护、隔离措施 ........................................................................... 76 11.8各种安全警示牌、标示标牌 .................................................................................. 79 11.9 管线的布置、安装安全措施 ................................................................................. 85 11.10用电安全管理措施 ................................................................................................ 85 11.11临建设施安全管理措施 ......................................................................................... 86 11.12机械安全管理措施。 ............................................................................................ 88 11.13 易燃易爆安全管理措施 ....................................................................................... 91 文件十二 环境保护措施 ..................................................................................................... 94

12.1环境保护体系 ........................................................................................................ 94 12.2实行环保目标责任制 ............................................................................................ 94 12.3施工生产厂区环境维护 ......................................................................................... 95 12.4污水排放措施 ........................................................................................................ 95 12.5水土保持措施 ........................................................................................................ 97 12.6其他环境保护措施 ................................................................................................ 98

卷 首 语

致 汉中黄河中型水电开发有限责任公司: 尊 敬的各位评委、专家:

借此之际,非常感谢贵公司给予我公司参与**********水电站砂石骨料供应标的竞标机会,通过我单位现场勘察,我公司已了解和熟悉了周边及现场情况,结合对本标段招标文件的研究与理解,现将本工程的重点及我公司实施本合同工程的总体思路归纳为卷首语以为评标导阅。

1、工程项目的总体认识

****水电站位于陕西省宁强县境内******干流上,坝址位于宁强县****镇上游约5km处,该电站上游规划有荷叶坝水电站,下游规划为阳平水电站。县乡级公路从坝址下游约2.6km左岸通过,宝成铁路由坝址下游右岸通过,在****镇有火车站。坝址距汉中市126.5km,距宁强县69.5km,外部交通比较方便。

本标段供应区砼高峰时段月平均浇筑强度20956m3。共需砼成品骨料约17.8万m3(其中砂5.4万m3,石子12.4万m3)。

2、工程特点认识

㈠ 砂石骨料生产系统建设工期短,施工强度大;

㈡砂石骨料供应时段分布不均衡,高峰期骨料需求量大,月生产强度高。 ㈢料场毛料级配不均衡,小石比例较大,筛分时原材料浪费严重。 ㈣水下毛料储量大,开采困难。

3、工作措施与对策

㈠ 态度及认识

我公司对**********水电站砂石骨料供应标段的建设和运行高度重视并投入极大的热情和努力,如果我们中标本工程的施工,我们将集中公司在四川境内的优势,以最佳的资源配置和先进的管理方式,全力以赴,保证砂石骨料的供应量,并借本系统的成功建设再次提升我局的市场信誉度和竞争实力,展示我公司特级企业在砂石骨料加工上具有的能力和水平。

㈡ 管理措施

公司将组建精干高效的管理机构,制定健全的项目管理制度和实施细则;对进场施工作业人员进行培训,并持证上岗;建立学习型施工企业,在施工过程中实行滚动式培训学习,不断提高施工作业队伍的整体素质。结合砂石骨料供应的特点,灵活配置作业队伍和专业管理人员,随时调配资源,实行动态管理,满足工程建设砂石骨料供应需要。

㈢ 资源保证

⑴ 施工队伍:承担****水电站工程砂石料系统的施工队伍,将以参加过西龙池水电站工程、黄河公伯峡水电站工程、黄河拉西瓦水电站工程、泰克则砂石骨料供应等项目的专业队伍为主体,抽调有着丰富砂石骨料系统施工技术和运行管理经验的技术人员。

⑵ 项目机构:砂石料供应标工程的管理机构组建将参照目前国内比较成熟的项目法施工管理经验,主要的管理人员均来自****有限公司长期从事砂石骨料系统的制作安装和运行任务的专业人员,项目经理、总工程师、技术、质量主要负责人将由我局参与白川水电站、南水北调项目、维坊峡山水库、扬黄甘肃专用工程等项目施工的专业技术人员担任,其资质符合招标文件要求。